Template

Free LPA checklist template

A good layered process audit starts with a good checklist: short, specific questions, each with a written expected answer, so every auditor at every layer checks the same thing the same way. This free Excel template gives you a ready-made structure and 26 example questions across safety, work instructions, quality checks, error-proofing, 5S, the control plan, and escalation. Use it on paper, in a spreadsheet, or import it straight into Loop.

What's in the template

The workbook has two sheets. Checklist holds the questions. How to use explains each column. The Checklist sheet has six columns:

ColumnWhat goes in itExample
CategoryThe group the question belongs to. Leave it blank to carry down the category from the row above.Error-proofing
CodeA short ID for the question, up to 12 characters.EP1
QuestionThe check the auditor answers. This is the only required column.Were the error-proofing devices at this station verified at the start of the shift?
ExpectationWhat a passing answer looks like, written so two auditors would reach the same answer.Verification record shows each device tested with its master or reject part at shift start.
LayerWhich layers ask the question: All, 1, 2, 3, L1, Level 2, or a list such as 2, 3.All
Pass answerYes if a Yes answer passes. No if a No answer passes. Blank means Yes.Yes

Why a "Pass answer" column? Some checks read most naturally as a question where "No" is the good answer, such as "Is any error-proofing device bypassed?" Marking the pass answer means the question can stay in plain language without being twisted into a double negative.

Example LPA questions

These questions are generic starting points, written for a typical machining, stamping, molding, or assembly station. Most are asked at every layer. A few are marked for L2 and L3, because they need more context or authority to check, such as comparing the station against the control plan or confirming that earlier findings were closed.

Safety & PPE

CodeQuestionExpected answerLayerPass answer
SP1Is the operator wearing every item on the station's posted PPE sign?Each item on the sign is worn as shown, for example safety glasses on the eyes, not on the head. No substitutions.AllYes
SP2Are machine guards, light curtains, and interlocks in place and working?Guards closed and fastened. Breaking the light curtain stops the cycle. No tape, jumpers, or other bypasses.AllYes
SP3Can the operator point to the nearest emergency stop and say when to use it?Points to the E-stop without searching and names at least one situation for using it.AllYes
SP4Are the walkways and exits around the station clear?Marked aisles free of pallets, hoses, and cords. Exit routes and fire equipment unblocked.AllYes

Work instructions

CodeQuestionExpected answerLayerPass answer
WI1Is the current revision of the work instruction posted at the station?Revision at the station matches the document system. Legible, with no handwritten changes.AllYes
WI2Watch one full cycle. Does the operator follow the work instruction steps in order?Every step done in the documented sequence, including built-in checks. No skipped or added steps.AllYes
WI3Is the operator trained and signed off for this operation?Operator's name is on the training matrix for this operation with a current sign-off.2, 3Yes
WI4Ask the operator which check at this station matters most for the customer. Can they explain it?Names the key characteristic or check, and says what to do if it fails.AllYes

Quality checks

CodeQuestionExpected answerLayerPass answer
QC1Is there a signed first-piece approval for the current job or setup?Approval record for this job, signed by an authorized person, completed before production parts were run.AllYes
QC2Are in-process check results recorded at the required frequency?An entry for every required interval since the shift started. Values within limits, or a recorded reaction.AllYes
QC3Is every measuring gauge at the station identified and inside its calibration date?Each gauge has an ID and a calibration label with a future due date. No damaged or unlabeled gauges in use.AllYes
QC4For any out-of-limit reading recorded this shift, was the reaction plan followed?Containment and notification done as the reaction plan says, and noted on the record.2, 3Yes
QC5Is any suspect or rejected product at the station missing a hold tag?No. Every suspect or rejected part is tagged and kept in the hold container, apart from good product.AllNo

Error-proofing

CodeQuestionExpected answerLayerPass answer
EP1Were the error-proofing devices at this station verified at the start of the shift?Verification record shows each device tested with its master or reject part at shift start.AllYes
EP2Is any error-proofing device bypassed or switched off?No. Any bypass is approved in writing, logged, and covered by a temporary containment check.AllNo
EP3Are the master and reject verification parts present, labeled, and in good condition?Parts are identified, stored at the station, and not worn or damaged.2, 3Yes

5S & Housekeeping

CodeQuestionExpected answerLayerPass answer
S1Does every tool and fixture at the station have a marked home, and is it there?Shadow board or labeled spots. No missing tools. Nothing stored that the job doesn't need.AllYes
S2Is every container labeled with its part number and status?Each container shows the part number and whether it is good, work in progress, or on hold.AllYes
S3Is the station free of leaks, spills, and debris?No oil, coolant, or scrap on the floor or machine surfaces. Any leak is reported to maintenance.AllYes
S4Does the station match its posted 5S standard or photo?Layout, labels, and storage match the posted standard.2, 3Yes

Control plan

CodeQuestionExpected answerLayerPass answer
CP1Do the checks done at this station match the control plan for this operation?Characteristics, method, sample size, and frequency on the check sheet match the current control plan.2, 3Yes
CP2Are the process settings inside the limits on the setup sheet?Displayed settings (for example temperature, pressure, speed) are inside the documented ranges.AllYes
CP3Pick one high-risk step from the PFMEA. Is its control in place and being used?The control listed in the PFMEA and control plan is at the station, with evidence it is being used.3Yes
CP4Are the findings from earlier audits at this station closed or on schedule?Each earlier finding is closed or within its due date, and the fix is visible at the station.3Yes

Escalation

CodeQuestionExpected answerLayerPass answer
ES1Ask: "What do you do if you find a bad part?" Does the answer match the escalation process?Stops, sets the part aside, and tells the team lead or quality right away, as the posted process says.AllYes
ES2Has the operator signed that they've read each quality alert posted at this station?Every posted alert is current and has the operator's sign-off.AllYes

How to adapt the template to your plant

The example questions show the format. Your own checklist should come from your own processes.

  • Start from risk. Pull the steps your PFMEA rates highest, the checks in your control plan, and anything behind a recent complaint or escape. Those deserve questions first.
  • Write the expected answer before you finalize the question. If you can't say what "yes" looks like in a sentence, the question is too vague to audit.
  • Keep each question to one observable thing. "Are guards in place and is the area clean?" is two questions.
  • Mix the methods. Use some document checks, some observation of a full cycle, and some questions you ask the operator directly.
  • Assign layers deliberately. Questions about the station itself suit every layer. Questions about whether the system works, like the control plan, training records, or closed findings, suit L2 and L3.
  • Plan to rotate. A larger bank, sampled a few questions at a time, finds more than the same short list asked every day.
  • Review it regularly. Retire questions that never fail, and add questions where audits or complaints show weakness.

Using it on paper or in a spreadsheet

You can print the Checklist sheet and add Yes / No / Comment columns for auditors to fill in, or keep results in the workbook. That's a reasonable way to start. As the program grows, the hard parts are usually:

  • knowing which audits were missed
  • making sure every failed check gets an owner
  • rotating questions without someone rebuilding the sheet every week

Import it straight into Loop

The template's columns match Loop's checklist import, so the file goes straight in:

  1. In Loop, an admin chooses Import your checklist and uploads the .xlsx file, or a .csv saved from it.
  2. Loop reads the columns (question, expectation, category, code, layer, and pass answer) and shows a preview of what it will add. Nothing is added until you confirm.
  3. Confirm, and the questions are in your question bank with their expected answers, codes, and layers. If the same question appears on more than one row with different layers, Loop adds it once and gives it each layer.

After importing, set each question's severity, which controls how often it comes up in the rotation, and choose which team is alerted when it fails. You can also import your resources and your roster of people from Excel or CSV.

From there, Loop:

  • schedules L1, L2, and L3 at the frequency you set for each layer
  • rotates questions by severity
  • opens a finding with an owner and a due date when a check fails
  • alerts the team you chose, including contacts who don't need a Loop login
  • shows done-vs-missed, coverage gaps, and Findings by Resource Group on the dashboards

Loop is one flat price per plant, with unlimited users and audits, for plants of any size. Start a 30-day free trial with no credit card required, or explore the demo plant to see a sample plant with fictional data.

FAQ

Is the template really free?

Yes. Download it, edit it, and use it however you like, with or without Loop.

Can I use it for checklists that aren't layered audits?

Yes, the format works for any yes/no checklist. In Loop, safety walks and other checklists are kept separate from your LPA numbers. They can ask every question every time or a sample each audit.

Does it work with CSV?

Yes. Save the Checklist sheet as CSV and Loop imports that too.

Do these questions meet my customer's LPA requirements?

They're generic examples, not a compliance checklist. Check your customers' current customer-specific requirements and AIAG's CQI-8 guideline, and build your questions from your own control plans and PFMEAs.

Questions about the template? Email support@looplpa.com.